Engineering and Design Schedule

Last reviewed 9 September 20262,666 words12 min read

IFC drawings, review cycles β€” the schedule that decides when construction can actually start

🟩 In one line: Design is scheduled as a chain per deliverable β€” produce β†’ check β†’ submit β†’ review (on the contract's review calendar) β†’ respond β†’ resubmit β†’ approve β†’ issue for construction β€” linked forward to the procurement or site activity that needs it, with progress earned on deliverable stages rather than time; on most Gulf projects the first six months of the critical path run through this chain, and it is the part of the schedule most often drawn as a single bar.

πŸ‘€ Who this is for: M/S, with J reading for the chain. Prerequisites: milestones-and-key-dates, procurement-and-long-lead-items, calendar-setup-and-holidays, progress-measurement-and-rules-of-credit.

e / c
First, let's be honest about why this page exists

"Design β€” 16 weeks" as one activity, followed by "Approvals β€” 8 weeks", is how design appears in most contractor programmes, whether the design is the employer's, the contractor's or a subcontractor's shop drawings. Neither bar can be statused, neither shows which package is late, neither links to the pile that can't start without it, and neither records the review period the contract actually allows β€” so when the consultant takes 31 days instead of 14, there is no activity to point at.

Design scheduling is repetitive, not difficult. The chain is the same for every deliverable; the numbers come from the contract; the links go to the site. What takes the time is the deliverable register β€” and that is the document the design team should already have.

🟨 The standard β€” what "good" looks like
SourceWhat it asks for (paraphrased)Consequence
FIDIC 1999 Cl 1.9 / 2017 Cl 1.9 (delayed drawings or instructions)Contractor gives notice when a drawing or instruction is needed by a date; failure to issue in time is an EOT/cost groundEvery employer-issued drawing package is a milestone with a "needed by" date the notice can cite
FIDIC 1999 Cl 4.1 (Red Book, contractor-designed parts) / Yellow Book 1999 Cl 5.2 / 2017 Red Cl 4.1, Yellow Cl 5.2Contractor's Documents submitted for review; Engineer's review period stated in the contract (21 days in the Yellow Book unless amended β€” verify)Review period is a contract number; goes on the review calendar
FIDIC 1999 Cl 8.3 / 2017 Cl 8.3Programme shows order and timing of design (where applicable), Contractor's Documents, procurementDesign chains are required programme content
NEC3/NEC4 Cl 21.2, 21.3Contractor submits design particulars; Project Manager replies within the period for reply (Contract Data); Contractor does not proceed until acceptedReview period = period for reply; proceed-after-acceptance is a hard link
NEC3/NEC4 Cl 27.1, 31.2Contractor obtains approvals from Others as required; programme shows dates for information from the ClientAuthority approvals as chains; client-information milestones
SCL Protocol 2nd ed., Core Principle 1; Guidance Part B (records)Programme reflects design and approval periods; records of submissions and responses keptSubmittal log dates are the actuals
AACE RP 38R-06Basis records design assumptions, review periods, resubmission allowanceSBM design section
GAO Schedule Assessment Guide, BP 1 and 2All work β€” including design and approvals β€” captured and logically linked to what depends on itDesign links forward to procurement and construction
DCMA 14-Point, Metrics 1, 8No open ends; no incomplete Task > 44 daysEvery design activity has a successor; no 16-week design bars
Convention (calendar-setup-and-holidays; multiple-calendars-and-float)Review periods stated in calendar days go on a 7-day calendar; working-day periods on the consultant's 5-day calendarApplied to every review activity

🟒 Rule: one chain per deliverable or logical package; review durations from the contract on the calendar the contract counts in; one resubmission cycle allowed unless the SBM says otherwise; every chain linked forward to the activity that needs the IFC; employer-issued information as milestones with a needed-by date; and progress earned on deliverable stages (30/60/90/IFC or submitted/approved), never on elapsed weeks.

How it actually works

1. Three kinds of design, one chain

KindWho producesWhat the contractor schedulesContract hook
Employer's design (traditional build)Employer's consultantMilestone per package: "IFC structural β€” Podium β€” issued"; needed-by date from the site logic; notice under Cl 1.9 when at riskFIDIC 1999/2017 Cl 1.9; NEC Cl 31.2 (information from the Client), Cl 60.1(3)
Contractor's design (D&B / EPC)Contractor's designerFull chain per deliverable, including internal checks and authority approvalsFIDIC Yellow Cl 5; NEC Cl 21
Shop drawings, submittals, samples, method statementsSubcontractors and suppliersChain per submittal package, linked to fabrication and siteEmployer's Requirements / spec section on submittals

2. The chain

StepActivityDurationCalendarNotes
1Produce (30% / 60% / 90% where staged)From designer's deliverable schedule; manhours Γ· teamOffice 5-daySteps in P6 for staged design (progress-measurement-and-rules-of-credit)
2Internal check / IDC3–5 daysOfficeOften skipped and always needed
3Submit0 (milestone)β€”Actual = transmittal date from the submittal log
4Review periodContract figure (14 / 21 calendar days; NEC period for reply)7-day where the contract says calendar days; consultant 5-day only if it says working daysThe contract number, not last month's experience
5Response received0β€”Actual from the log; code A/B/C/D or accept/not accept
6Revise and resubmit5–10 daysOfficeOne cycle allowed in the baseline; SBM states it
7Second reviewContract figure7-day
8Approved / no objection0β€”
9Issue for Construction2–5 daysOfficeOr 0 if IFC = approval
10SuccessorProcurement (order placement) or site activityFS, hard

Steps 4–8 collapse to a single review if the contract or the SBM assumes first-time approval β€” write the assumption down; most Gulf projects average 1.5–2 cycles on structural and MEP packages.

3. Packaging β€” how many chains

ProjectChainsBasis
Mid-rise building, contractor shop drawings only40–80Per discipline per zone: structural shop drawings by level band; MEP coordinated drawings per floor group; faΓ§ade; finishes schedules; major equipment submittals
D&B hospital150–300Design deliverable register by discipline and stage, plus authority approval chains (civil defence, municipality, utilities)
EPC process plant500+Per document from the master document register; engineering progress measured on it (oil-gas-and-epc)

One chain per drawing is too many; one per discipline is too few. Package at the level the reviewer responds at β€” the transmittal.

4. Linking forward β€” the need date

Every chain ends in the activity that cannot proceed without it. Working backwards from that activity's early start gives the need date; the chain's finish must sit on or before it. Where it doesn't, the design is on the critical path and the programme says so. Employer-issued packages get a Start On or After milestone at the contract or agreed release date with the reference β€” and the need-date comparison is the basis of the Cl 1.9 notice.

Chain ends inTypical need-date logic
Structural IFC (level band)Rebar procurement (bar bending schedule) and formwork fabrication for that band
MEP coordinated drawings (floor group)Sleeve/embed setting-out before the slab pour of the first floor in the group; first fix
FaΓ§ade shop drawingsFaΓ§ade fabrication order β€” the 26-week chain (tender-programme)
Equipment submittal (chillers, switchgear, lifts)Purchase order release; fabrication lead
Authority approval (civil defence, building permit)Mobilisation, or the inspection stage it gates

5. Measuring design progress

Design does not earn progress by the week. Two acceptable methods (progress-measurement-and-rules-of-credit):

MethodSteps and weightsFor
Deliverable stageStarted 10 / IDC issued 30 / Submitted 60 / Approved 90 / IFC 100Shop drawings and submittals
Design stage30% 25 / 60% 30 / 90% 30 / IFC 15D&B design packages

Each step earned on a transmittal or log entry. Remaining durations re-forecast from the achieved review cycle: if the consultant is returning packages in 24 calendar days against 14, the remaining review activities are 24 (with the deviation recorded as a notice-able event, not silently absorbed).

6. The submittal log is the actuals

The design/document controller's submittal log β€” submission date, response date, code, resubmission date β€” is the quantity sheet for design. Actual starts and finishes on the chain come from it; the monthly reconciliation compares log dates to P6 dates; the trend in consultant review duration is reported like any other achieved rate.

7. SBM design section

Review periods per document type with clause references; resubmission allowance; authority approval periods as numbered assumptions; deliverable register revision; need-date table for the top 20 packages.

πŸ“œ Late information β€” the record

Under FIDIC Cl 1.9 the contractor must give notice stating when the drawing is needed and the consequences; the schedule's need-date table is that statement, and the milestone with its Start On or After and reference is the record. Under NEC, information from the Client later than the date on the Accepted Programme is a compensation event under Cl 60.1(3) β€” the programme has to show the date first. A design chain that exists only as a 16-week bar cannot support either.

πŸŸ₯ Where people go wrong
  1. One bar for design, one for approvals. Cannot be statused, linked or argued. Chain per package with the contract's review period.
  1. Review period from experience, not contract. 21 days shown because that's what the last consultant took; the contract says 14. The baseline carries 14 (the entitlement); the achieved 21 is recorded as a deviation and noticed. Doing it the other way round gives the review time away.
  1. Review on the consultant's 5-day calendar when the contract says calendar days. 14 calendar days becomes 20. 7-day calendar for calendar-day periods (multiple-calendars-and-float).
  1. No resubmission cycle. Every package approved first time in the baseline; the first B-code adds two weeks nobody planned. One cycle allowed and stated in the SBM.
  1. Design not linked forward. The IFC milestone dangles; the pile starts regardless. Every chain FS into the procurement or site activity that needs it β€” the need date is the whole point.
  1. Employer's packages missing. Structural IFC assumed at week 6 with no milestone; week 10 it hasn't arrived and there is nothing in the programme to cite. Milestone, reference, needed-by, Cl 1.9 notice.
  1. Progress by elapsed time. "Design 60%" because ten of sixteen weeks have passed; nothing submitted. Steps on deliverable stages, earned on the log.
βš–οΈ When you're challenged

"Why are there 70 design activities on a build-only contract? The employer designs." Sixty of them are our shop drawings and submittals β€” structural, MEP coordination, faΓ§ade, equipment β€” each with the 14-day review the Employer's Requirements allow and one resubmission. The other ten are milestones for the Employer's IFC packages with the dates we need them. Without those ten there's nothing to give notice against when a package is late.

"The consultant has 21 days. You've shown 14." The contract says 14 calendar days, section 4.1 of the ER. Fourteen is the entitlement and the baseline shows it. The consultant has averaged 23 on the first six packages β€” that's in the narrative as an achieved rate, remaining reviews are forecast at 23, and the notices are in. If I baseline 21, I've given a week away on every package.

"Design is 45% complete β€” ten weeks of twenty-two are done." Twenty-two percent by deliverable stage: 8 of 36 packages submitted, 2 approved. The manhours may be 45% spent, but the site can build from approved drawings, not from weeks. The stage-weighted figure is the one in the report, and the forecast is from the achieved submission rate.

πŸ“„ Related pages
✏️ Worked example

Design-and-build clinic in Abu Dhabi, FIDIC Yellow Book 1999-based, review period 21 days (Cl 5.2, unamended β€” verify), authority approvals: municipality building permit, civil defence, health authority. Deliverable register: 42 design packages, 3 authority approvals, 18 subcontractor submittal packages.

Chain (extract)ProduceIDCReview 1 (7-day cal)ReviseReview 2IFCSuccessorNeed dateFinish vs need
STR-01 Foundations 90% β†’ IFC15 d4 d21 cd7 d21 cd3 dRebar BBS / piling orderC+11 wkC+12.3 wk β†’ critical, 1.3 wk late
STR-02 Superstructure L1–L320 d4 d21 cd7 d21 cd3 dFormwork fabrication L1C+19 wkC+17 wk, 2 wk float
MEP-04 Coordinated L118 d5 d21 cd8 d21 cd3 dSleeves before L1 slab pourC+22 wkC+21.6 wk, 0.4 wk float β†’ near-critical
AUTH-01 Building permitβ€”β€”6 wk (A03, municipality)β€”β€”0Mobilisation / pilingC+8 wkC+8 wk, on need date
AUTH-02 Civil defence design approvalβ€”β€”4 wk (A04)2 wk4 wk0MEP fabrication ordersC+26 wkC+24 wk
SUB-07 Chillers submittal10 d2 d21 cd5 d21 cd0PO release; 22-wk fabricationC+14 wkC+13.4 wk

Findings at baseline: foundations design 1.3 weeks late to the piling need date β€” resolved by splitting STR-01 into pile design (IFC first) and pile cap/raft (second package), which brought the piling order inside the need date and put the raft design on Float Path 2. Progress on all 42 packages by design-stage steps; submittal log as the actuals; consultant review trend reported monthly. Month 4: average review 26 calendar days against 21; four Cl 1.9-style notices issued citing the need-date table; remaining reviews re-forecast at 26 with the entitlement at 21 recorded in the narrative.

πŸ“– References
  • FIDIC Conditions of Contract for Construction, 1999, Cl 1.9, 4.1, 8.3; 2017, Cl 1.9, 4.1, 8.3; FIDIC Conditions of Contract for Plant and Design-Build, 1999, Cl 5.2; 2017, Cl 5.2 (check the edition in your contract)
  • NEC3 / NEC4 Engineering and Construction Contract, Cl 21.2, 21.3, 27.1, 31.2, 60.1(3) (check the edition in your contract)
  • SCL Delay and Disruption Protocol, 2nd ed. (2017), Core Principle 1; Guidance Part B
  • AACE International RP 38R-06, Documenting the Schedule Basis
  • GAO Schedule Assessment Guide (GAO-16-89G), Best Practices 1, 2
  • DCMA 14-Point Schedule Assessment, Metrics 1, 8
  • Oracle Primavera P6 Professional User Guide β€” Activity Steps; Calendars; Milestones

From the field

Experience from working planners. Unreviewed β€” read it as experience, not guidance.

Add what you know about engineering and design schedule. What worked, what the consultant pushed back on, what you would do differently next time. A paragraph is plenty.

Contributors get their name and one link on the site β€” your own templates, course or consultancy. We take nothing and hold nothing.

Add your experience