Setting Up a P6 Project

Last reviewed 9 September 20262,041 words9 min read

The settings to get right before you type an activity β€” because most of them can't be fixed cleanly afterwards

🟩 In one line: Fifteen minutes in Admin Preferences, Project Details and Scheduling Options before the first activity saves weeks of unexplained date movement later β€” this page is the checklist, in the order you click.

πŸ‘€ Who this is for: J/M. Prerequisites: none; links out to the pages that argue each setting.

e / c
First, let's be honest about why this page exists

Most planners inherit a database, copy an old project and start typing. The old project carried someone else's percent-complete type, someone else's critical-path definition and a calendar with 8 hours a day on a site working 10. Nobody notices until the first update, when every duration shows as 1.25 times what was typed and the critical path highlights half the network.

Every setting below is argued properly on its own page. This page is just the order to set them and the value to choose.

🟨 The standard β€” what "good" looks like
SourceWhat it asks for (paraphrased)Setting it touches
AACE RP 38R-06Schedule basis records calendars, settings, methodsEverything below goes in SBM section on tool settings, with a screenshot
DCMA 14-Point, Metrics 1–5, 12Logic, leads, lags, relationship types, hard constraints, critical path testDefaults for new activities; scheduling options
GAO Schedule Assessment Guide, BP 1 and 6Capture all activities; confirm the critical pathWBS, activity ID scheme, Longest Path
PMI Practice Standard for Scheduling, 2nd ed.Schedule model settings documented and consistentSame
Client schedule specifications (typical Gulf)Often mandate: hours per day, Longest Path, physical % complete, activity ID format, codingCheck the spec before this page β€” it overrides it

🟒 Rule: set Admin Preferences first, then Project Details, then Scheduling Options, then calendars, codes and UDFs β€” and screenshot the lot into the SBM before the first activity exists.

How it actually works

1. Admin Preferences (Admin β†’ Admin Preferences) β€” database-wide, do once, agree with the database owner

TabSettingValueWhy
Time Periods"Use assigned calendar to specify the number of work hours for each time period"TickedDurations display in days per each calendar's real hours (hours-per-day-and-duration-display)
Earned ValueTechnique for computing performance % completeActivity % completePhysical % drives EV; changed per WBS where a rule of credit applies
Earned ValueTechnique for computing ETCPF = 1 (or as SBM states)Recorded in SBM; argued in earned-value-basics
ID LengthsActivity ID, WBS code, resource IDβ‰₯ 20 / 20 / 20Zone-coded IDs run long
Data LimitsActivity codes, baselines per projectRaise if neededThree baselines per project minimum

2. Project Details (Enterprise β†’ Projects, select project, Details at bottom)

TabSettingValueWhy
GeneralProject ID, name, Responsible Manager (OBS)Per contract numberingID appears on every export
GeneralStatusActivePlanned/What-If projects don't summarise
DatesPlanned StartContract commencementNever later than the first activity
DatesMust Finish ByBlankIt is a hidden Finish On or Before on the whole project; use a constrained milestone instead
DatesData Date= Planned Start at set-upMoves only in the monthly update
DefaultsDuration TypeFixed Duration & UnitsDurations don't move when resources change (p6-duration-types-explained)
DefaultsPercent Complete TypePhysicalNever Duration on production work
DefaultsActivity TypeTask DependentOthers chosen deliberately, per activity
DefaultsCalendar6-day site calendar (project-level)The most common calendar becomes the default
DefaultsAuto-numberingPrefix per WBS scheme; increment 10Room to insert
SettingsCharacter for WBS separator"."Client spec may dictate
SettingsBaseline for earned value calculationsProject baselinePoints EV at the accepted baseline, not a user's
SettingsDefine critical activitiesLongest PathFloat ≀ 0 breaks across calendars (critical-path-vs-longest-path)
CalculationsActivity % complete based on activity stepsTicked where steps are usedRules of credit via steps
CalculationsLink Budget and At Completion for not started activitiesTickedStops budgets drifting before start
CalculationsWhen updating actual units or costSubtract actual from At CompletionKeeps At Completion honest; SBM records choice
CalculationsRecalculate actual units when duration % changesUntickedActuals come from records, never from %
CalculationsLink actual and actual this periodTickedPeriod reporting works

3. Scheduling Options (Tools β†’ Schedule β†’ Options, F9)

Set once, screenshot into the SBM, check on every received file. Full table on scheduling-options; the short version:

SettingValue
When scheduling progressed activitiesRetained Logic
Calculate SS lag fromActual Start
Define critical activities asLongest Path
Compute total float asFinish Float
Calendar for scheduling relationship lagPredecessor Activity Calendar
Make open-ended activities criticalUnticked (tick only to hunt dangles)
Schedule automatically / Level during scheduleBoth unticked
Log to fileTicked, every run
Advanced: multiple float pathsFree Float; 5–10 paths; end at contractual completion milestone

4. Calendars (Enterprise β†’ Calendars)

Create project calendars, not global, unless the database owner has enterprise standards. Global calendars travel in every XER and pollute other databases.

CalendarHours/dayDaysExceptions
Site 6-day10 (8.5 mid-Jun to mid-Sep for external work)Sat–ThuEid, National Day, Ramadan reduced hours as date exceptions
Curing 7-day24AllNone
Office 5-day8Sun–Thu (or Mon–Fri per client)Public holidays
Consultant review7-day, 24 hAllNone β€” only where the contract counts calendar days

Set each calendar's own Time Periods button to its real hours. Details on calendar-setup-and-holidays.

5. Structures and codes

ItemSet-upNote
WBSContract β†’ phase β†’ area/level β†’ discipline; ≀ 6 levelswbs-structure-design
Activity codes (project-level)Area, Level, Discipline, Subcontractor, Change Ref, Split FromProject codes export cleanly; global codes don't
UDFsDuration Basis (text), Qty, Unit, Rate, Crew (numbers)crew-and-manhour-formulas
Notebook topicsLogic Basis, Forecast Basis, Change Basis, Recovery BasisCreated once in Admin Categories
Activity ID schemeAREA-LVL-DISC-NNN, e.g. T1-L05-BLK-020Readable without opening the activity
MilestonesContract commencement; every contractual key date; planned completion; contractual completion (constrained FOoB)milestones-and-key-dates

6. User Preferences (Edit β†’ User Preferences) β€” per user, per machine, not per project

TabSettingValue
Time UnitsDurations shown inDays, 0 decimals (hours when checking lags)
Time UnitsUnits/TimeUnits/day
DatesFormatDD-MMM-YY, no time, or time shown when diagnosing
CalculationsResource assignments: preserve units, duration and units/timePer SBM

These do not travel with the XER. Every reviewer opening your file with 8-hour display will see different durations β€” the SBM screenshot is your defence.

πŸŸ₯ Where people go wrong
  1. Copying last year's project as the template. Someone else's percent type, constraints and global codes come with it. Build from a clean project, or strip the copy to zero activities and audit every tab first.
  1. Must Finish By set to the contract date. It constrains everything and hides real negative float behind a project-level constraint nobody sees in the activity table. Blank; constrained milestone instead.
  1. Default percent type left on Duration. Every production activity then earns progress by the calendar. Physical, before the first activity exists.
  1. Global calendars and global codes for a single project. They arrive in every XER the client, the consultant and the next subcontractor imports. Project-level for everything project-specific.
  1. Admin Preferences hours-per-day not set to "use assigned calendar". A 10-hour site day displays a typed 10 days as 12.5. The correction is one tick β€” and it is the first thing checked on a received file.
  1. No screenshot in the SBM. Six months later nobody can prove what the settings were at baseline, and the client's reviewer has changed three of them in their own copy.
βš–οΈ When you're challenged

"Why can't I just start typing? The settings can be changed later." Some can. Percent type can't be changed cleanly once actuals exist, hours-per-day changes redisplay every duration, and the critical-path definition changes what's red in every report you've already issued. Fifteen minutes now.

"The client's spec says Total Float ≀ 0 for critical. You've set Longest Path." Both are set β€” the report filter uses the spec's float definition, the scheduling option uses Longest Path so the path is continuous across the curing and consultant calendars. The SBM records both and the narrative reports both where they differ.

"Your durations look different on my machine." Your User Preferences show 8-hour days; the site calendar is 10. The SBM screenshot shows the setting; tick "use assigned calendar" in Admin Preferences and they'll match.

πŸ“„ Related pages
✏️ Worked example

Set-up sheet for a 14-storey residential tower in Abu Dhabi, pasted into SBM section 3 before activity 1:

ItemValue
Project ID / nameAUH-RT14 / Residential Tower, Plot 14
Planned start / data date15 Jan; 15 Jan
Must Finish ByBlank
DefaultsTask Dependent; Fixed Duration & Units; Physical %; calendar "AUH-RT14 Site 6d 10h"
CriticalLongest Path (report filter also shows TF ≀ 0)
Scheduling optionsAs table above; screenshot attached
Calendars (project)Site 6d 10h (summer 8.5h 15 Jun–15 Sep); Curing 7d 24h; Office 5d 8h; Review 7d 24h
Activity codesArea (T1, POD, EXT); Level (B2–L14, RF); Discipline (STR, BLK, MEP, FIN, FAC); Subcontractor; Change Ref; Split From
UDFsDuration Basis; Qty; Unit; Rate; Crew
Notebook topicsLogic Basis; Forecast Basis; Change Basis; Recovery Basis
ID schemeAREA-LVL-DISC-NNN, increment 10
MilestonesCommencement; Structure topping-out KD; Building envelope KD; Planned completion; Contractual completion (FOoB 30 Apr)
Admin PreferencesUse assigned calendar: ticked; EV = Activity %; ETC PF = 1

Time taken: 40 minutes including calendar exceptions. Time it would have cost to fix at Update 3: two days and a re-issued narrative.

πŸ“– References
  • AACE International RP 38R-06, Documenting the Schedule Basis
  • DCMA 14-Point Schedule Assessment, Metrics 1–5, 12
  • GAO Schedule Assessment Guide (GAO-16-89G), Best Practices 1, 6
  • PMI Practice Standard for Scheduling, 2nd ed.
  • Oracle Primavera P6 Professional User Guide β€” Admin Preferences; Project Details (General, Dates, Defaults, Settings, Calculations); Schedule Options; Calendars; Activity Codes; User Defined Fields; User Preferences (field labels as in P6 Professional v20; earlier versions differ)

From the field

Experience from working planners. Unreviewed β€” read it as experience, not guidance.