S-Curves: Early, Late and Actual
Last reviewed 9 September 20261,833 words8 min read
Three lines, one envelope β and what to say when the actual leaves it
π© In one line: The early and late curves come from the accepted baseline's early and late dates, the actual comes from physical percent weighted by manhours or cost, and the forecast comes from the current update β the actual should sit inside the envelope, and where it sits tells you how the job is going before you open a single activity.
π€ Who this is for: Junior planners producing the monthly curve; mid-level planners explaining it. Prerequisites: P6-baselines-assign-and-maintain, Progress-measurement-and-rules-of-credit, Resource-loading-and-histograms.
First, let's be honest about why this page exists
Most S-curves in Gulf monthly reports are one planned line and one actual line, both drawn from the current schedule, weighted by nothing in particular. They cannot show slippage because the planned line moves every month with the update, and they cannot show whether being 4 % behind matters because there is no late curve to say how much room there was.
An S-curve is a summary of the schedule, not a substitute for it. Built from the right three sources it answers the client's first question β "are we on programme?" β with a shape, and hands the second question β "by how much?" β to the longest path.
π¨ The standard β what "good" looks like
| Source | What it says (paraphrased) | Use it for |
|---|---|---|
| FIDIC 1999 Cl 4.21 / 2017 Cl 4.20 | Monthly progress report includes charts comparing actual and planned progress (check the edition in your contract) | The curve is a contractual deliverable |
| FIDIC 2017 Cl 8.3 | Supporting report to the programme includes anticipated progress and resources per period (check against your copy) | Baseline curve submitted with the programme |
| NEC3 / NEC4 Cl 32.1 | Revised programme shows actual progress and its effect on remaining work | Actual vs plan is required content |
| PMI Practice Standard for Scheduling, 3rd ed. | Cumulative planned and earned curves as schedule model outputs (check against your copy) | Definitions |
| AACE RP 38R-06 | Planned progress curve and its weighting basis documented in the SBM | Weighting declared once |
| GAO Schedule Assessment Guide, Best Practice 5 and 9 | Progress measured against a valid baseline; cost and schedule integrated | Baseline source |
| Hub convention | Weight by manhours (labour) and separately by cost; planned = Project baseline early dates; late = Project baseline late dates; actual = Physical % Γ weight; forecast = current update; never weight by duration or activity count | Your defaults |
π’ Rule: two curves from the accepted baseline, one from the quantity sheet, one from the current update β all four labelled with their source and revision on the chart.
How it actually works
1. The four lines.
| Line | Source | How it is built | What it means |
|---|---|---|---|
| Planned (early) | Project baseline, early dates | Baseline budgeted units spread across each activity's baseline early startβfinish, cumulated by period | The fastest the accepted programme allowed |
| Late | Project baseline, late dates | Same units spread across late startβfinish | The slowest that still meets the contractual completion; below this you are late |
| Actual (earned) | Current update | Physical % Γ budgeted units per activity, cumulated to each data date; history from previous updates, never recomputed | What has been done |
| Forecast | Current update, early dates | Remaining units spread across current early dates from the data date | Where the current schedule says the actual will go |
The envelope between early and late is the total float of the whole programme expressed as work. An actual inside it is on programme; on the late line is zero float; below it is negative float in output terms.
2. Weighting. Manhours for the labour curve, cost for the value curve; both from the same assignments (Cost-loading-and-cash-flow). Duration-weighting makes a 200-day LOE worth more than a 10-day pour; activity-count weighting makes a milestone worth a slab. Neither survives the first review question. State the weighting on the chart.
3. In P6. Activity Usage Profile (View β Show on Bottom, verify against version in use): Display β cumulative; show Budgeted Labor Units (or Total Cost); tick Baseline bars for Early and Late; Actual and Remaining for the current project; timescale monthly. Export via the Activity Usage Spreadsheet to the workbook β the report chart is drawn in Excel so the actual history is preserved across baseline revisions and the lines can be labelled properly. Baseline early and late series are exported once per accepted revision and stored.
4. Reading it β in order.
| Read | How | What it says |
|---|---|---|
| Position | Actual vs early and late at the DD | Inside = on programme; below late = behind; above early = front-loaded or rules-of-credit problem |
| Horizontal gap | From actual, read across to the early curve | Weeks behind the planned output β indicative, not the date |
| Slope | Actual's gradient over the last 3 months vs the planned gradient for the same period | Whether the site is producing at the rate the plan needed |
| Forecast shape | Forecast line's peak gradient vs the best achieved gradient | A forecast steeper than anything achieved is a ramp nobody has proven |
| Tail | Where the forecast flattens | T&C gating; a long flat tail usually means energisation or authority chain |
Then go to layout 04: the curve says whether; the longest path says how much and why.
5. Per-node curves. One project curve for the cover; curves by WBS Level 2 (structure, envelope, MEP, finishes, T&C) in the body. A project curve inside the envelope can hide an MEP curve 12 weeks below its late line.
π₯ Where people go wrong
- Planned line from the current schedule. It moves every month, so the actual always looks close. Planned and late come from the Project baseline in the register and change only at a baseline revision (flagged on the chart).
- No late curve. One planned line gives no sense of room. Without the late curve, 6 % behind is unreadable; with it, the actual is either still inside or it is not.
- Weighted by duration. LOE prelims and 400-day design bars dominate; the curve is 30 % complete while the site is still in the ground. Manhours or cost, declared in the SBM.
- Actual history recomputed. A rules-of-credit change or baseline revision re-draws past months. Each DD's earned value is written once to the workbook and never changed; a revision is a flagged step, not a redraw.
- Curve read as a delay measurement. "The actual is six weeks behind the planned line, so we are six weeks late." Output lag and longest-path variance are different numbers; report both, side by side.
- Forecast line missing or identical to planned. Either the forecast has not been produced or the update was not rescheduled. The forecast starts at the actual, on the data date, and ends at the current forecast completion.
- No labels. A curve without data date, baseline name, weighting and revision is a picture. The footer carries all four.
βοΈ When you're challenged
"Your S-curve shows 62 % against 68 % planned. That's 6 % late." Six percent of output behind the early curve β and still just inside the late curve, which is why the contractual milestone shows plus four days on the longest path. The two numbers agree: behind on volume, not yet late on the date. Next month's slope decides which way it goes.
"Why does the planned line differ from last month's report?" It shouldn't, and it doesn't β the planned and late lines are from BL1 in both. The forecast line has moved, because the update moved; that's the dashed one. If they look different it's the axis scale, and I'll fix that.
"The forecast curve catches up by month 20. How?" Honestly, it needs a gradient 25 % steeper than the best month achieved so far. That's the recovery plan's manpower ramp, and it's the reason the histogram check is in the same report. If the ramp isn't there by month 17, the forecast isn't either.
π Related pages
- Earned Value Basics: SPI and CPI β the same PV/EV data as ratios
- Earned Schedule β the horizontal read, made rigorous
- Cost Loading and Cash Flow β the value curve and the cash-in curve built from it
- P6 Baselines: Assign and Maintain β where the early and late series come from
- Slippage and Trend Analysis β the trend register the curve summarises
- Monthly Progress Report β where the curve sits in the pack
- Redirect: s-curves-explained and early-vs-late-vs-actual-curves are merged into this page
βοΈ Worked example β Doha office tower, labour curve at DD month 12
BL0 accepted; BAC 3,120 kmh; weighting manhours.
| Month | Early (kmh) | Late (kmh) | Actual (kmh) | Forecast (kmh) |
|---|---|---|---|---|
| 3 | 182 | 124 | 176 | β |
| 6 | 442 | 299 | 401 | β |
| 9 | 787 | 572 | 702 | β |
| 12 | 1,229 | 962 | 1,014 | 1,014 |
| 15 | 1,716 | 1,417 | β | 1,398 |
| 18 | 2,184 | 1,892 | β | 1,830 |
| 21 | 2,613 | 2,379 | β | 2,301 |
| 24 | 2,964 | 2,808 | β | 2,749 |
| 26 | 3,120 | 3,120 | β | 3,036 |
| 27 | β | β | β | 3,120 |
Read: Actual 1,014 sits between late (962) and early (1,229): inside the envelope, tracking 5 % above the late line. Horizontal read to the early curve: about 6 weeks of output lag. Slope months 9β12: 104 kmh/month actual against 147 planned for the same window. Forecast reaches BAC in month 27 β one month past the baseline β and requires 157 kmh/month in months 18β21, which is 12 % above the best achieved month. Layout 04 shows β18 working days at contractual completion. Narrative sentence: "Cumulative earned manhours 32.5 % against 39.4 % planned (BL0); inside the early/late envelope; longest path β18 working days, driver MEP-L08-DUC-120; forecast gradient months 18β21 exceeds best achieved by 12 % and depends on the MEP manpower ramp in recovery option R-3."
π References
- FIDIC Conditions of Contract for Construction 1999, Cl 4.21; 2017, Cl 4.20, 8.3 (check the edition in your contract)
- NEC3 / NEC4 ECC, Cl 32.1 (check the edition in your contract)
- PMI, Practice Standard for Scheduling, 3rd ed. (check the edition and section in your copy)
- AACE International RP 38R-06, Documenting the Schedule Basis
- GAO, Schedule Assessment Guide, GAO-16-89G, Best Practices 5 and 9
- Oracle Primavera P6 Professional User Guide β Activity Usage Profile; Activity Usage Spreadsheet (check against your P6 version)
From the field
Experience from working planners. Unreviewed β read it as experience, not guidance.
Add what you know about s-curves: early, late and actual. What worked, what the consultant pushed back on, what you would do differently next time. A paragraph is plenty.
Contributors get their name and one link on the site β your own templates, course or consultancy. We take nothing and hold nothing.
Add your experience