P6 Baselines: Assign and Maintain

Last reviewed 16 September 20268 min read

Project vs user baseline β€” one is the contract's yardstick, the other three are yours to compare against

🟩 In one line: A P6 baseline is a frozen copy of the project stored inside it; the Project Baseline is one per project, shared by every user, points at the accepted baseline from the register and drives earned value; the User Baselines (primary, secondary, tertiary) are per user, point at anything you want to compare against β€” last month's update, the tender programme, a recovery plan β€” and never at anything contractual.

πŸ‘€ Who this is for: J/M. Prerequisites: baseline-approval-and-control, importing-and-exporting-xer.

e / c

First, let's be honest about why this page exists

The contract page settled what a baseline is and how it is accepted. This page is the button-level version: how the accepted programme becomes a baseline object inside P6, how to point the right columns at it, and how to avoid the three operations that destroy it β€” Restore, Update Baseline and Replace on import.

The commonest damage is not deliberate. A colleague assigns their own comparison as the Project Baseline, the EV columns quietly switch to measuring against last month, and the S-curve in the report is wrong for two cycles before anyone asks why BEI jumped to 1.00.

🟨 The standard β€” what "good" looks like

SourceWhat it asks for (paraphrased)Consequence in P6
GAO Schedule Assessment Guide, BP 10Maintain a baseline schedule; document each revision and its approvalOne Project Baseline = the register's current accepted revision
DCMA 14-Point, Metrics 13 and 14CPLI and BEI measured against the approved baselineThe variance columns and BEI count read the Project Baseline
AACE RP 38R-06Schedule basis identifies the baseline and its revisionBaseline name carries revision and data date
PMI Practice Standard for Scheduling, 2nd ed.Baseline as the approved version for comparison; changes controlledUser baselines for analysis, Project Baseline for control
FIDIC 1999 Cl 8.3 / 2017 Cl 8.3; NEC Cl 31.3, 32.2Accepted programme (NEC) / programme submitted and not rejected (FIDIC)The accepted one becomes BLn in the register and the Project Baseline in P6
Convention (baseline-approval-and-control)Named BL0-Accepted-DD 01Jan25-Rev1; register for life of job; accepted XER archived read-only; never Restore except into a sandboxThis page's procedure

🟒 Rule: Project Baseline = the current accepted revision in the register, named to match, changed only when the register changes; User Baselines = anything else; and a baseline is never Restored, Updated or overwritten in the live project.

How it actually works

1. The four slots

SlotScopeSet atWhat reads itConvention
Project BaselineOne per project, all usersProject β†’ Assign Baselines β†’ Project BaselineVariance – BL Project columns; BL Project bars; earned value (when Project Details β†’ Settings β†’ "Baseline for earned value calculations" = Project baseline)Current accepted revision from the register
Primary User Baseline (BL1)Per userProject β†’ Assign Baselines β†’ PrimaryVariance – BL1 columns; BL1 barsPrevious accepted update (slippage-and-trend-analysis)
Secondary (BL2)Per userSameBL2 columns / barsTender programme, or the previous baseline revision
Tertiary (BL3)Per userSameBL3 columns / barsRecovery plan target, or any what-if

Baselines also sit inside the project as objects: Project β†’ Maintain Baselines lists every baseline saved, regardless of whether it is assigned to a slot. Admin β†’ Admin Preferences β†’ Data Limits sets the maximum number per project β€” raise it early; five to ten is comfortable on a three-year job.

2. Creating the baseline from the accepted file

StepActionNote
1Written acceptance received naming revision and data dateRegister row opened
2Accepted XER archived read-onlyThe file, not the database object, is the record
3Project β†’ Maintain Baselines β†’ Add β†’ "Convert another project to a new baseline of the current project", pointing at the imported accepted filePreferred: the baseline is exactly the accepted file. "Save a copy of the current project" is acceptable only if the live project is byte-identical to what was accepted
4Name: BL0-Accepted-DD 15Jan25-Rev0; Baseline Type: Initial Planning / Customer Sign-Off (or whatever the admin's list uses); Last Update Date notedName matches the register and the archive file
5Project β†’ Assign Baselines β†’ Project Baseline = BL0-Accepted-DD 15Jan25-Rev0Everyone now measures against it
6Project Details β†’ Settings β†’ Baseline for earned value = Project baselineOtherwise EV follows each user's primary
7Layout bars: Project Baseline bar on; BL1 bar for the previous updateSix layouts (p6-layouts-and-filters) updated
8SBM tool-settings section: baseline name, slot assignmentsScreenshot

3. Monthly

  • After each accepted update, Maintain Baselines β†’ Add β†’ Save a copy of the current project, named "Upd08-Accepted-DD 01Sep25". Assign as Primary User Baseline next month. This is how the previous-update comparison exists without a second project.
  • Project Baseline untouched.

4. Baseline revision (an EOT, agreed acceleration, re-scope)

Same eight steps for BL1-Accepted-DD 01Dec25-Rev0. Project Baseline reassigned to BL1. BL0 stays in Maintain Baselines β€” never deleted β€” and can sit in a user slot for the transition-month comparison (splitting-in-progress-activities). Register and SBM updated together.

5. The three operations that destroy a baseline

OperationWhereWhat it doesRule
RestoreMaintain Baselines β†’ RestoreTurns the baseline back into a standalone project and removes it from the baseline listOnly in a sandbox database, on a copy, when you need to export or inspect it. Never in the live project
UpdateMaintain Baselines β†’ UpdateCopies selected current-project data into the baseline (dates, logic, resources, by filter)Never on an accepted baseline. It rewrites the yardstick to match the work
Replace Existing Project on importImport β†’ Import ToDeletes the project and every baseline inside it, then recreates from the fileNever on a production project

Delete is a fourth: Maintain Baselines β†’ Delete removes the object. Only ever for a stray what-if copy, never for anything that appears in the register.

6. Getting a baseline out of P6

The XER export does not carry baselines. To send one: send the archived accepted XER (the register points at it); or Copy the baseline (Maintain Baselines β†’ Copy) into a sandbox, Restore it there, export; or use XML export, which can include assigned baselines. Whichever, the transmittal says which.

7. Reading the columns

ColumnMeaning
BL Project Start / FinishDates in the Project Baseline
Variance – BL Project Finish DateCurrent finish βˆ’ Project Baseline finish; positive = later (check against your copy)
BL1 Start / Finish; Variance – BL1 Finish DateSame against the Primary User Baseline
BL Project DurationBaseline OD
Planned Value Cost / Labor UnitsFrom the baseline for EV

Activities added after the baseline show blank BL dates; P6 can substitute planned dates for missing baselines (Project Details β†’ Settings β†’ "Earned value calculation β†’ use planned dates when baseline missing" β€” verify label), which should be off in a submission so added scope is visible as added.

πŸŸ₯ Where people go wrong

  1. Project Baseline pointed at last month. Every variance column and the EV curve now measure a month, not the contract. Project Baseline = register; last month goes in BL1.
  1. "Save a copy of the current project" after the live project has already been edited. The baseline is not the accepted file. Convert the imported accepted XER instead.
  1. Restore to "have a look." The baseline leaves the list and becomes a project; a week later someone schedules it. Copy β†’ sandbox β†’ Restore there.
  1. Update Baseline to add the variation. The yardstick now contains the change and the variance disappears. Variations are visible precisely because they have no baseline dates.
  1. Data limit at the default. Third baseline refuses to save mid-update. Raise the limit at set-up.
  1. Baseline name that says nothing. "Baseline 3 (copy)" cannot be matched to a register row or a letter. Revision and data date in the name, every time.

βš–οΈ When you're challenged

"Your S-curve moved but nobody changed the baseline." Someone reassigned the Project Baseline to Upd 07 for a comparison. Assign Baselines shows it; I've set it back to BL1-Accepted-DD 01Dec25 and the curve matches the register again. Comparisons go in the user slots β€” that's what they're for.

"Send the baseline inside the XER." XER doesn't write baselines. The accepted baseline file is in the register as BL1, issued 4 December; I'll re-attach it, or send XML with the baseline embedded if that suits your import better.

"Just update the baseline with the new dates so the report is green." Update Baseline rewrites the accepted programme to match what happened, and the variance vanishes with it. The report is measuring correctly; the slippage is real. If the client wants a new baseline it's a written acceptance and a register row.

πŸ“„ Related pages

✏️ Worked example

Baseline state on a Doha office tower at Update 11 (DD 1 December), the month a 25-day EOT triggered BL1:

Maintain BaselinesTypeAssigned slotPurpose
BL0-Accepted-DD 15Jan25-Rev0Customer Sign-OffSecondary (BL2), this month onlyTransition comparison
BL1-Accepted-DD 01Dec25-Rev0Customer Sign-OffProject BaselineRegister current; EV; DCMA 13/14
Upd10-Accepted-DD 01Nov25Monthly UpdatePrimary (BL1)Slippage vs previous update
Recovery-R2-Target-DD 01Dec25What-IfTertiary (BL3)Target date shown alongside forecast
Upd01 … Upd09Monthly UpdateNoneKept; register history

Data limit set to 20 in month one. Project Details β†’ Settings β†’ EV baseline = Project baseline. Register row 2 reads: BL1, acceptance letter E-1044 dated 18 Nov, data date 1 Dec, archived file DOH-OT_BL1_DD01Dec25_v20.xer, SBM Rev 1.

πŸ“– References

  • GAO Schedule Assessment Guide (GAO-16-89G), Best Practice 10
  • DCMA 14-Point Schedule Assessment, Metrics 13, 14
  • AACE International RP 38R-06, Documenting the Schedule Basis
  • PMI Practice Standard for Scheduling, 2nd ed.
  • FIDIC Conditions of Contract for Construction, 1999 and 2017, Cl 8.3; NEC3/NEC4 ECC Cl 31.3, 32.2 (check the edition in your contract)
  • Oracle Primavera P6 Professional User Guide β€” Maintain Baselines; Assign Baselines; Project Settings (earned value baseline); Admin Preferences β†’ Data Limits (field labels as in P6 Professional v20; earlier versions differ)

From the field