Revised Baseline vs Recovery Schedule

Last reviewed 9 September 20261,960 words9 min read

Two documents, routinely confused โ€” one changes the plan, the other changes the yardstick

๐ŸŸฉ In one line: A recovery schedule shows how the contractor will get back to the existing contractual date at its own initiative; a revised baseline replaces the plan of record and needs the other party's written acceptance โ€” issuing one and calling it the other is how projects lose both their EOT and their measurement.

๐Ÿ‘ค Who this is for: J/M/S. Prerequisites: baseline-approval-and-control, forecasting-honestly, float-ownership-and-contract.

e / c
First, let's be honest about why this page exists

"We've re-baselined" is said on site to mean at least three different things: the contractor issued a recovery programme, the Engineer accepted a revised programme under Cl 8.3, or an EOT was awarded and the completion date moved. Only one of those changes the yardstick that BEI, CPLI and the trend register are measured against.

The confusion is not innocent. A recovery schedule that is quietly adopted as the baseline erases the slippage it was written to recover. A revised baseline that is treated as "just a recovery" leaves the project measuring itself against a date the contract no longer contains. Get the vocabulary right and most of the argument disappears.

๐ŸŸจ The standard โ€” what "good" looks like
SourceRecovery scheduleRevised baseline
FIDIC 1999 Cl 8.6 / 2017 Cl 8.7Engineer may require revised methods when progress is too slow; Contractor adopts them at its own cost unless the cause is the Employer'sโ€”
FIDIC 1999 Cl 8.3 / 2017 Cl 8.3Revised programme whenever inconsistent with actual progress (a recovery schedule is one such revision)The same clause; acceptance does not by itself change the Time for Completion
FIDIC 1999 Cl 8.4 / 2017 Cl 8.5โ€”Award of EOT changes the Time for Completion โ€” the trigger for a baseline revision
NEC3/NEC4 Cl 32.1โ€“32.2Revised programme shows how the Contractor plans to deal with delaysEvery accepted revision becomes the Accepted Programme โ€” but Completion Date moves only via a CE
NEC3/NEC4 Cl 36Acceleration by quotation and agreement โ€” the instructed form of recoveryAgreed acceleration changes the Completion Date and the Prices
NEC3 Cl 63.3 / NEC4 Cl 63.5โ€”CE assessment moves planned Completion and hence the Completion Date
SCL Protocol 2nd ed., Core Principles 15 and 16Contractor mitigates at no additional cost unless instructed; acceleration is compensable only when instructed or agreedDistinguishes voluntary recovery from paid acceleration
GAO Schedule Assessment Guide, Best Practice 10โ€”Maintain a baseline; document every revision with rationale and approval
AACE RP 38R-06โ€”SBM revised only with a baseline revision
DCMA Metrics 13, 14โ€”Measured against the approved baseline, not a working target

๐ŸŸข Rule: a recovery schedule keeps the contractual completion date and shows a way back to it; a revised baseline changes the plan of record โ€” and only the second needs a signature from the other side.

How it actually works

The comparison

Recovery scheduleRevised baseline
Question it answers"How do we get back to the date?""What is the plan of record now?"
TriggerForecast completion later than contract; Engineer's Cl 8.6/8.7 request; internal decisionAwarded EOT; agreed acceleration (NEC Cl 36); major re-scope; a contract clause requiring periodic re-baseline
Who initiatesContractorEither โ€” but always concluded by written acceptance
Contractual completion dateUnchangedChanged (or plan restated to a new agreed date)
Forecast completionStays as the network says until measures are evidencedReset to the new baseline plan
CostContractor's, unless instructed accelerationAgreed through the EOT/CE/acceleration mechanism
P6 statusA Reflection / copy named "Recovery Plan R1 โ€” DD 01 Sep"; never assigned as Project BaselineNew baseline in the register, e.g. BL1-Accepted-DD 01Sep25-Rev0; assigned as Project Baseline
BEI / CPLI / trend measured againstThe existing accepted baselineThe new baseline, with the revision flagged in the trend register
SBMUnchanged (recovery narrative records the changed assumptions)Revised per AACE 38R-06
Narrative nameRecovery NarrativeRevised Baseline Narrative + Baseline Acceptance letter
ApprovalEngineer/PM "receives" or "accepts" it as a Cl 8.3 revision โ€” no change to entitlementEngineer/PM accepts in writing, naming revision and data date
LifetimeWeeks to a few months; tracked weekly; replaced or abandonedUntil the next accepted revision
What it must not doBecome the baseline by default; waive EOT entitlementHide slippage by restarting the trend; absorb un-awarded claims

The three dates that live side by side

DateSourceShown as
Contractual completionContract + awarded EOTsConstrained milestone (Finish On or Before)
Forecast completionCurrent update networkUnconstrained; reported with basis
Recovery targetRecovery planSeparate row; reported with measures, cost, approvals โ€” never as the forecast

The recovery target replaces the forecast only when the measures behind it are evidenced (crew on site, instruction issued, procurement confirmed). Until then two dates, two bases.

The three routes a recovery schedule can take

RouteWhat happensBaseline effect
It worksForecast converges on the contractual date over successive updatesNone โ€” baseline never moved
It is accepted as paid acceleration (NEC Cl 36 / FIDIC agreed variation)Completion Date and Prices changeBaseline revision, register row, SBM revised
It failsSlippage continues; EOT position argued; recovery replacedNone โ€” the failed recovery stays in the archive as evidence of mitigation (SCL CP 15)

The abuse to watch for

Re-baselining to the current forecast at month 9, with no EOT and no agreement, moves the yardstick to wherever the project happens to be. BEI resets to 1.0, the trend register shows zero variance and the 40 days of slippage vanish from the reports. Reviewers under GAO BP 10 and DCMA look for exactly this: a baseline revision without a documented contractual trigger. The trend register convention โ€” continuous, revision flagged, movement carried across โ€” is the protection.

๐ŸŸฅ Where people go wrong
  1. Assigning the recovery plan as the P6 Project Baseline. BEI and CPLI now measure against a target nobody signed, and the accepted baseline is one careless "Restore" from being lost. Recovery lives as a Reflection or named copy.
  1. Calling an accepted Cl 8.3 revision a new baseline. Acceptance of a revised programme is acceptance that it shows actual progress. It does not move the Time for Completion. Only Cl 8.4 / 8.5 does that.
  1. Issuing a recovery schedule without the reservation sentence. "Submitted without prejudice to the Contractor's entitlement under Cl 8.4 / Cl 60.1." Without it, the other side reads the recovery as an admission that the delay is yours.
  1. Treating the recovery target as the forecast. The narrative reports 30 April because the recovery says so, while the network still says 14 June. Two dates, two rows, until the measures are evidenced.
  1. Re-baselining after an EOT without revising the SBM. New completion date, new logic in places, old basis document. The SBM and the baseline register move together.
  1. Re-baselining to hide slippage. No EOT, no agreement, no re-scope โ€” just a new baseline at the current forecast. Every trend register that carries the movement across the revision will show it, and so will the reviewer.
โš–๏ธ When you're challenged

"You issued a recovery programme and we accepted it. That's the baseline now." You accepted it as a revised programme under 8.3 โ€” it shows how we plan to deal with the delay. The Time for Completion hasn't changed, so the baseline hasn't either. If the Employer wants the recovery adopted as the plan of record with the acceleration paid for, that's an agreement under a different clause and we'd document it as one.

"We got 25 days of EOT. Just update the recovery and carry on." The EOT moves the contract date, so the baseline register gets a new row and the SBM is revised โ€” that's a baseline revision. The recovery plan then targets the remaining 15 days against the new date. Both things happen; they're different documents.

"Why are there two completion dates in your report?" Forecast is what the network says with today's rates. Target is what the recovery plan achieves if the second formwork set arrives and the night shift is approved. When those are on site the forecast will move towards the target. Until then, showing one date would be showing a wish.

๐Ÿ“„ Related pages
โœ๏ธ Worked example

An office tower in Doha, FIDIC 1999, contract completion 31 March. At Update 09 (DD 1 October) forecast completion is 10 May โ€” 40 days late, of which 25 days are attributed to a late Employer-supplied transformer (claim submitted, notice ref C-118) and 15 to the Contractor's own structure slippage.

DateEventDocumentBaseline registerTrend register
5 OctRecovery Plan R1 issued targeting 31 March, "without prejudice to Cl 8.4 entitlement"Recovery Narrative R1; P6 copy "Recovery R1 โ€” DD 01Oct"; not a baselineNo change (BL0 remains)Forecast 10 May, target 31 Mar, both shown
20 OctEngineer accepts R1 as revised programme under Cl 8.3Engineer's letterNo changeNo change
18 NovEOT of 25 days determined under Cl 8.4; contract completion โ†’ 25 AprilDetermination letterNew row: BL1-Accepted-DD 01Dec25-Rev0; SBM Rev 1Row flagged "BL1 accepted +25 days"; movement series continues
5 DecRecovery Plan R2 issued targeting 25 April (15 days to recover, all Contractor's)Recovery Narrative R2No changeForecast per Upd 11 network; target 25 Apr
1 MarUpd 14 forecast converges to 27 April; R2 measures evidencedUpdate 14No changeForecast 27 Apr; target retired

One EOT, one baseline revision. Two recovery plans, zero baseline revisions. The 40 days of history stayed in the trend register throughout.

๐Ÿ“– References
  • FIDIC Conditions of Contract for Construction, 1999, Cl 8.3, 8.4, 8.6; 2017, Cl 8.3, 8.5, 8.7 (check the edition in your contract)
  • NEC3 / NEC4 Engineering and Construction Contract, Cl 32.1, 32.2, 36, 63.3 (NEC3) / 63.5 (NEC4) (check the edition in your contract)
  • SCL Delay and Disruption Protocol, 2nd ed. (2017), Core Principles 15, 16
  • GAO Schedule Assessment Guide (GAO-16-89G), Best Practice 10
  • AACE International RP 38R-06, Documenting the Schedule Basis
  • DCMA 14-Point Schedule Assessment, Metrics 13 and 14
  • Oracle Primavera P6 Professional User Guide โ€” Maintain Baselines; Assign Baselines; Reflections

From the field

Experience from working planners. Unreviewed โ€” read it as experience, not guidance.

Add what you know about revised baseline vs recovery schedule. What worked, what the consultant pushed back on, what you would do differently next time. A paragraph is plenty.

Contributors get their name and one link on the site โ€” your own templates, course or consultancy. We take nothing and hold nothing.

Add your experience