Notice Requirements and Records

Last reviewed 9 September 20262,273 words10 min read

The paperwork that wins or loses it

🟩 In one line β€” More EOT claims fail on a missed notice than on a bad analysis: FIDIC gives 28 days from awareness, NEC gives 8 weeks, both as conditions precedent β€” and the analysis that follows is only as good as the daily reports, updated programmes and dated correspondence that exist to support it. Send the notice early, send it even when unsure, and keep the records as if the dispute has already started.

πŸ‘€ Who this is for β€” Everyone. Juniors need to know what to flag to the contracts team and when; seniors need the clause numbers. Short page, dense on purpose.

e / c
First, let's be honest about why this page exists

The planner is usually the first person on the project to know a delay has started β€” the activity didn't start, the drawing didn't arrive, the access wasn't there. The planner is also usually the last person who thinks it's their job to say so in writing. Three weeks later, at the monthly meeting, someone mentions it; a letter goes out the following week; it's day 32. Under FIDIC 1999 Cl 20.1, the claim is gone.

Records are the other half. A TIA is only as strong as the dates in it, and the dates come from daily reports that were filled in properly, photos that were taken, and updates that were statused truthfully. No amount of P6 skill recovers a claim with no notice and no records.

🟨 The standard β€” what "good" looks like

Notice clocks

ContractNoticeFrom whenConsequence of missing itThen what
FIDIC 1999 Cl 20.128 daysWhen the Contractor became aware, or should haveTime for Completion not extended; claim barredFully detailed claim within 42 days; contemporary records kept; Engineer responds within 42 days
FIDIC 2017 Cl 20.2.128 daysSameBarred; Engineer must give notice of the time-bar (20.2.2) within 14 days, or the notice is deemed validFully detailed claim within 84 days (20.2.4); Engineer agrees or determines within 42 days under Cl 3.7 (20.2.5)
NEC3 / NEC4 Cl 61.38 weeksBecoming aware of the eventNo change to Prices, Completion Date or Key Dates β€” unless the PM should have notified it and didn'tPM responds within 1 week (61.4); quotation within 3 weeks (62.3)
NEC3 Cl 16 / NEC4 Cl 15Early warning "as soon as" awareAny matter that could delay, increase cost, or impair performanceNot a bar, but assessment may be reduced as if warning had been given (NEC3 63.5 / NEC4 63.7)Risk (NEC3) / early warning (NEC4) register and meeting

Records

ReferenceRequirement
FIDIC 1999 Cl 20.1Contractor keeps contemporary records; Engineer may inspect and instruct further records
FIDIC 2017 Cl 20.2.3Same, with the term defined β€” records prepared or generated at the same time as the event
FIDIC 1999/2017 Cl 6.10Records of personnel and equipment on site, submitted monthly
FIDIC 1999/2017 Cl 4.21Monthly progress reports with prescribed content, including comparison of actual and planned progress
NEC3/NEC4 Cl 32Revised programme showing actual progress, effects of implemented CEs, and changes to planned Completion
SCL Protocol Core Principle 1Programme and records β€” the Contractor should keep records and the Employer should insist on them; Part B Β§1 lists six categories
SCL Core Principle 3Follow the contractual procedure; notices should be given even where the delay's effect is not yet known

🟒 Rule to remember: notice within 28 days under FIDIC, 8 weeks under NEC, counted from when you should have known β€” send it before you're sure, and write today's record as if it will be read by a stranger in three years.

How it actually works

Who sends the notice. The contracts or commercial team signs it. The planner triggers it. Agree on the project that any of these goes to the contracts manager the same day: an Employer-risk activity that hasn't started on its planned date; a drawing, approval or access more than a few days overdue; an instruction that changes scope or sequence; an unusual site condition; an Engineer's comment that amounts to an instruction.

What a notice needs to say. Less than people think. That an event has occurred, what it is, roughly when, that it is or may be an Employer-risk event under clause X, and that the Contractor intends to claim time (and cost, if relevant). Effect not yet known is fine β€” say so and promise particulars. The template-delay-notice page has the letter. What kills a notice is being a "report" β€” buried in a monthly narrative, or worded so softly ("we note with concern…") that the Engineer can argue it wasn't a notice at all.

Counting the days. From awareness, or when you should have been aware β€” the second limb means the planned date on the accepted programme is usually the trigger. Calendar days. If in doubt, send it. A notice for something that turns out not to be a delay costs nothing; a missed notice for something that is costs everything.

Ongoing events. Give the first notice, then interim particulars monthly (FIDIC 1999 Cl 20.1 fourth paragraph; 2017 Cl 20.2.6). The monthly update and narrative can carry them if they're explicit and referenced back to the notice number.

The records that matter for delay

RecordWho keeps itWhy it mattersCommon failure
Updated programme, each data date, with narrative stating the critical pathPlannerThe base for every TIA; the concurrency evidenceUpdated but not archived; narrative says nothing about criticality
Delay register (event, dates, activities, notice ref)PlannerTurns scattered events into a claim skeletonStarted in month 18
Daily site report: labour by trade and location, plant, weather, work done, work prevented and whySite engineer / foremanProves who was where and what stopped them"Ongoing works" as the only entry; no location; no "prevented" column
Dated, geotagged photographs, weekly per zoneSite teamSettles arguments about when a thing existedTaken only when something looks good
Access / handover certificates, signed both sidesContractsFixes the date the Employer says was differentVerbal handover, no paper
RFI, submittal and approval logs with dates in and outDocument controlProves the review took 40 days, not 14Log not exported; system access lost at project end
Meeting minutes with actions and datesContracts / PMContemporaneous acknowledgement by the other sideUnsigned drafts; disputed later
Correspondence registerDocument controlShows the notice went in, and whenEmails without register numbers
Delivery notes, fabrication dispatch, inspection requests and resultsQA/QC, procurementFragnet durations come from theseKept by the subcontractor only

The planner's own discipline. Archive each update as an XER and a PDF on the data date, with the narrative. Note the critical and near-critical paths in every narrative β€” one paragraph. Keep the delay register in the same folder. When you leave the project, hand all of it over (see handing-over-a-schedule). These three habits are, in practice, the difference between a claim that can be built and one that can't.

Gulf context. Time bars are generally enforced in the UAE, KSA and Qatar; some tribunals have softened them on good-faith grounds under the civil codes, but nobody should plan on that. Treat the clock as absolute.

πŸŸ₯ Where people go wrong
  1. Waiting until you're sure it's a delay. The clause counts from awareness of the event, not from confirmation of its effect. SCL Core Principle 3 says notify anyway. Day 29 is too late however clear it's become.
  1. Notice by narrative. The monthly report mentions the late drawings on page 14. The Engineer will say that isn't a notice under Cl 20.1, and will often be right. Separate letter, clause quoted, claim intention stated.
  1. Daily reports that record nothing useful. Twenty pages of "works ongoing", no locations, no "prevented" column. When the fragnet needs to show the fixers stood idle for four days, the daily report shows forty fixers on site and nothing else.
  1. Updates overwritten, not archived. The month-9 XER was updated in place to become month 10. There is no month 9. The TIA for the month-9 event now starts from a reconstruction, and reconstructions are disputed.
  1. Letting the subcontractor hold the records. Delivery notes, fabrication dates, their daily allocation β€” all with them. When the relationship sours or the sub goes, so does the evidence.
  1. No one owns the trigger. The planner assumes contracts knows; contracts assumes the site told them. Agree in writing who triggers what, and put the trigger list on the wall.
βš–οΈ When you're challenged

"Your notice is day 31. Time-barred." "The event is the late access, which was due 12 March under the accepted programme. Access was granted piecemeal β€” the last section came on 19 March, and our notice references that date. From 19 March the letter is day 24. If the Engineer's position is that awareness dates from the 12th, we'd note our notice under Cl 20.1 was also given prospectively on 8 March when the Employer's utility first advised a possible delay β€” letter 187, attached."

"You haven't shown any records for the idle period." "Daily reports for 4 to 9 May are attached; the 'work prevented' column shows Zone C fixers redeployed to Zone A housekeeping, with the reason given as awaiting access. The photos from the 6th show the fenced-off area. And the Engineer's own representative countersigned the report on the 7th."

"Why should we accept a reconstructed programme for the base?" "You shouldn't have to, and it isn't one. The April update was submitted on 3 May β€” transmittal 0142 β€” and your comments on it were closed on 14 May. That's the base. The only reconstruction is statusing it forward 11 days to the day before the event, from the daily reports, and each date is footnoted."

πŸ“„ Related pages
✏️ Worked example

Data centre shell and core, Riyadh, FIDIC 2017. The trigger list agreed at kick-off and how it worked on one event.

DateWhat happenedAction
Mon 3 FebPlanned date for Engineer's approval of chiller submittal (accepted programme, activity PR-CH-030, 21-day review period)Planner flags to contracts: due today, not received
Tue 4 FebContracts sends "awaiting approval" reminder β€” not a noticeLogged as DR-11 in delay register, status "watching"
Mon 10 FebStill not received; chiller PO can't be placed; procurement lead 26 weeksPlanner confirms PR-CH-030 has 4 days float; runs forward: critical on 7 Feb
Tue 11 FebNotice under Cl 20.2.1 issued β€” letter 231. Event: late approval; clause: 1.9 / 8.5(a) as a delay by the Employer's Personnel; effect: not yet quantified; particulars to followDay 8 from planned date. Register updated with letter ref
26 FebApproval received (23 days late)DR-11 closed for cause; effect ongoing through procurement
3 MarInterim particulars in monthly update narrative, referencing letter 231; prospective TIA: 17 working days to completionReflection archived: base 31 Jan update, impacted, comparison
28 AprFully detailed claim (day 76 from notice, within 84) with actual PO date, vendor's revised delivery, updated TIA: 15 working daysRecords attached: submittal log, letter 231, PO, vendor correspondence, daily reports for the affected plant-room activities
9 JunEngineer's determination under Cl 3.7 β€” 15 daysβ€”

The entire claim ran on a register entry made on 4 February, a letter sent on the 11th, and an XER archived on the 3rd of March. The analysis took two days. The records took eight minutes a day for the whole project.

πŸ“– References
  • FIDIC Conditions of Contract for Construction 1999, Cl 1.3, 4.21, 6.10, 8.4, 20.1; FIDIC 2017, Cl 1.3, 3.7, 4.20, 6.10, 8.5, 20.2.1–20.2.7 (check the edition in your contract)
  • NEC3 ECC Cl 16, 32, 61.3, 61.4, 61.5, 62.3, 63.5; NEC4 ECC Cl 15, 32, 61.3, 61.4, 62.3, 63.7 (check the edition in your contract)
  • Society of Construction Law, Delay and Disruption Protocol, 2nd ed. (2017), Core Principles 1 and 3; Part B Β§1 (records)
  • AACE International RP 29R-03, Forensic Schedule Analysis β€” source validation and records
  • Oracle Primavera P6 Professional User Guide β€” Reflections, Export XER, Notebook Topics

From the field

Experience from working planners. Unreviewed β€” read it as experience, not guidance.

Add what you know about notice requirements and records. What worked, what the consultant pushed back on, what you would do differently next time. A paragraph is plenty.

Contributors get their name and one link on the site β€” your own templates, course or consultancy. We take nothing and hold nothing.

Add your experience