P6 EPS, OBS and Enterprise Data

Last reviewed 16 September 20267 min read

The structures above the project β€” and why a shared database goes wrong when nobody owns them

🟩 In one line: The EPS says where a project sits, the OBS says who is responsible and who can see it, and enterprise data (global calendars, codes, resources, UDFs) is shared by every project in the database β€” which is why a planner should create as little of it as possible and never import it casually.

πŸ‘€ Who this is for: J/M. Prerequisites: setting-up-a-p6-project. Companion to p6-global-vs-project-data and cleaning-an-xer-before-import.

e / c

First, let's be honest about why this page exists

On a standalone laptop none of this matters. On a company database with 40 projects and 12 planners it matters every week: someone imports a subcontractor's XER with "Keep Existing" unticked and every project's 6-day calendar now has the subcontractor's holidays; someone creates a global activity code called "Area" that clashes with the one already there; someone deletes an EPS node and takes three archived projects with it.

The fix is not technical. It is knowing which four things are shared, agreeing who owns them, and treating everything else as project-level.

🟨 The standard β€” what "good" looks like

SourceWhat it asks for (paraphrased)Relevance
PMI Practice Standard for Scheduling, 2nd ed.Schedule model components structured consistently; data integrity maintainedEnterprise data is the shared component
AACE RP 38R-06Schedule basis records the coding structures and calendars usedWhich are global and which are project must be stated
GAO Schedule Assessment Guide, BP 1Capture all activities within a defined structureEPS/WBS relationship
DCMA 14-PointAssessed per projectAn EPS node summarising several projects is not a schedule for assessment
Client schedule specifications (typical Gulf)Often prescribe activity code names and calendar namesPrescribed names are project codes in your database, mapped on export

🟒 Rule: EPS and OBS belong to the database owner; a planner creates project-level codes, project calendars and project UDF values, and treats every global object as read-only unless the owner says otherwise.

How it actually works

1. The three structures

StructureWhat it isWho owns itWhat a planner does with it
EPS (Enterprise Project Structure)Hierarchy of nodes holding projects β€” e.g. Company β†’ Region β†’ Client β†’ ProjectDatabase admin / PMOPlaces the project in the right node; never creates or deletes nodes without agreement
OBS (Organisational Breakdown Structure)Hierarchy of responsible managers; drives security β€” a user sees only projects under OBS nodes they are assigned toDatabase adminAssigns the project's Responsible Manager; asks admin for access changes
WBS (per project)The project's own breakdown, below the EPSThe plannerBuilds it (wbs-structure-design)

The EPS is not a WBS for the whole company. Summarising a node gives you a roll-up of unrelated projects β€” useful for a portfolio dashboard, meaningless as a schedule.

2. Enterprise (global) data β€” what is shared

ObjectGlobal / project optionsConvention
CalendarsGlobal, Resource, ProjectProject for anything project-specific; global only for enterprise standards the admin maintains
Activity codesGlobal, EPS, ProjectProject for Area, Level, Discipline, Sub, Change Ref, Split From; global only for enterprise reporting codes (e.g. Sector)
Project codesGlobal onlyAdmin sets (Client, Region, Sector, Status)
Resources and rolesGlobal onlyOne resource pool; planner adds resources only under the node agreed for the project; quantity-loaded jobs use non-labour resources per trade
Cost accountsGlobal onlyMirror the company's cost code structure; admin owns
UDFsGlobal definitions; values per projectDefinitions created once by admin (Duration Basis, Qty, Unit, Rate, Crew); values are the planner's
Notebook topicsGlobal (Admin Categories)Created once: Logic Basis, Forecast Basis, Change Basis, Recovery Basis
Currencies, units of measureGlobalAdmin
Filters, layouts, reportsGlobal or UserUser for personal; global only when the team agrees a standard
BaselinesPer projectPlanner, per the baseline register

3. Where it goes wrong β€” the import

An XER carries the project and every global object it references. On import with default options, incoming global objects overwrite yours. The production rule from cleaning-an-xer-before-import: received files go into a sandbox database first; production import config = Keep Existing / Do Not Import for global data, Delete unticked; original file archived unedited.

Incoming objectSafe import settingConsequence of getting it wrong
Global calendar with the same name as yoursKeep ExistingEvery project's holidays change
Global activity code "Area"Do Not Import (or Keep Existing)Code values merge; filters break
ResourcesDo Not Import unless agreedPool polluted with 300 duplicate labour resources
Cost accountsDo Not ImportCompany cost structure gains foreign nodes
UDF definitionsKeep ExistingDuplicate "Qty" fields, one empty

4. Housekeeping the admin should run

TaskFrequencyTool
Orphan global calendars (no assignments)QuarterlyEnterprise β†’ Calendars, "Used By"
Duplicate activity codes / valuesQuarterlyEnterprise β†’ Activity Codes
Resource pool hygieneQuarterlyEnterprise β†’ Resources, filter unused
Archived projects moved to an "Archive" EPS node, status InactiveAt project closeEnterprise β†’ Projects
OBS access reviewQuarterlyAdmin β†’ Users; OBS

5. What the planner records

In the SBM tool-settings section: EPS node, OBS responsible manager, list of project calendars, list of project activity codes, list of global objects relied on (with owner). On export for submission, note in the transmittal which global objects the file carries β€” so the receiving planner can set their import options before, not after.

πŸŸ₯ Where people go wrong

  1. Creating global codes for a single project. They follow every XER out of the database and clash with someone else's the moment they land. Project-level, always, unless the admin asks for global.
  1. Importing straight into production. The subcontractor's calendar overwrites the company's. Sandbox database first; Keep Existing / Do Not Import in production.
  1. Deleting an EPS node to tidy up. Every project under it goes too, with its baselines. Move projects to an Archive node and set them Inactive; deletion is the admin's decision.
  1. Using EPS summary as a programme. The client asks for the "master schedule" and receives a summary of five unrelated projects with a critical path that means nothing. Inter-project logic needs a deliberate set-up, not a node.
  1. Resources created per project in the global pool. "Mason", "Mason (T1)", "Mason – Tower", "Masons" β€” four rows, one trade. Agree resource names with the admin before loading.
  1. No named owner. When nobody owns the enterprise data, everyone edits it. One name, written in the department's procedure, with the right to say no.

βš–οΈ When you're challenged

"The client wants their code names exactly. I need to create them globally." Create them as project codes with the client's names β€” project codes export with the same name and the client's database reads them identically. Global only changes what happens inside our database, and there it causes clashes.

"I can't see the project. Give me access." Access is by OBS, not by project. Your user needs the OBS node the project sits under β€” that's a five-minute change for the admin and it's the right way round, because it also controls who can edit the baseline.

"Just import the sub's file, I need the dates today." Ten minutes into the sandbox and you'll have the dates today. Ten seconds into production and every project on the database may have the sub's Fridays working.

πŸ“„ Related pages

✏️ Worked example

A contractor's database in Doha, 28 active projects. A planner on a mixed-use scheme imports a faΓ§ade subcontractor's XER directly into production with default options. The file carried a global calendar named "Standard 6 Day" β€” the same name as the company's enterprise calendar β€” with Friday working and no Eid exceptions.

EffectExtentTime to repair
Company "Standard 6 Day" calendar overwritten19 projects using itRestore exceptions from SBM records, reschedule each, verify no date change via Schedule Comparison β€” 3 working days
112 subcontractor resources added to the poolGlobalDelete after confirming no assignments β€” half a day
Global activity code "Zone" created alongside existing "Area"1 projectRe-map and delete β€” 1 hour
Monthly submissions for 4 projects delayedβ€”Reputational

The procedure written afterwards: one named database owner; sandbox database on every planner's machine; production import config saved as a template "Prod-Safe" (Keep Existing / Do Not Import, Delete unticked); transmittal note listing global objects in every outgoing XER. Cost of the incident: roughly 5 planner-days. Cost of the procedure: one afternoon.

πŸ“– References

  • PMI Practice Standard for Scheduling, 2nd ed.
  • AACE International RP 38R-06, Documenting the Schedule Basis
  • GAO Schedule Assessment Guide (GAO-16-89G), Best Practice 1
  • Oracle Primavera P6 Professional User Guide β€” Enterprise Project Structure; Organizational Breakdown Structure; Global and Project Data; Import/Export (field labels as in P6 Professional v20; earlier versions differ)

From the field